Enter the day as it happened, let the crew agreement price the late meal and the overtime as their own pay lines, and carry the same numbers into payroll.

Open video in a new tab

Day two on stage. Call was at seven. Lunch was called at one-thirty, six and a half hours later. Nobody on the floor was watching the clock, but the crew agreement was. Under most crew agreements a late first meal costs a meal penalty, and every hour past the daily or weekly limit is paid as overtime.

On a paper timecard, that half hour is easy to miss. It shows up weeks later, when a crew member asks why their check is short, and by then it means a correction, a second check, and someone who waited for money they were owed.

The film above follows one week for one boom operator on UPP. It uses a demonstration production and invented crew, not a client account. The numbers on screen are the numbers UPP calculated for that week.

The day goes in the way it happened

Each day is entered as it happened: call, first meal out, first meal in, wrap. The timecards can come from a spreadsheet, a PDF, a photo of the paper card, or be typed in by hand, and they land together in one batch. The coordinator reviews each day and creates draft timesheets from the batch.

In the film, the boom operator's Tuesday reads call 07:00, wrap 17:00, no meal break at all. Wednesday reads call 07:00, lunch 13:30 to 14:00, wrap 17:30. That is the late lunch.

Read against that crew member's agreement

When the timesheet is calculated, UPP reads each day against the agreement attached to that crew member's classification. In the film that is a union Microphone Boom Operator classification in Los Angeles County.

The result is a timesheet with the overtime and the meal penalty on their own lines, not buried in a total:

  • Regular hours (32.00 h): $2,276.80
  • Overtime (8.00 h): $853.80
  • Meal penalties: $167.50
  • Gross pay: $3,298.10
  • Fringes and benefits: $719.14
  • Total cost: $4,017.24

Nobody had to go looking for the penalties: on this timesheet, most of the $167.50 comes from Tuesday's missed meal and the rest from Wednesday's late one. Whoever reviews the timesheet can see where each dollar came from.

The same numbers carry into payroll

Once the timesheet is approved, the same figures go into the payroll run. The timesheet shows the run it belongs to, the employee withholding line by line (federal, Social Security, Medicare, California withholding and SDI), the employer taxes, and the check amount. In the film the check is $2,180.43.

Nothing is typed twice: the payroll run starts from the timesheet the coordinator approved.

What this does not replace

UPP calculates what the agreement and the entered times say. It does not decide whether a meal was called late; the times entered do. If the call or meal times on the card are wrong, the pay will be wrong, so the review step still matters. We covered how to review a week without losing the story of the day in Approve production timesheets without losing the story of the day. What changes is that the review happens while the day is still fresh, not weeks later when someone files a claim.